Objekt nr | Projekt | Land | Effekt/kW | Teknisk beskrivning |
---|---|---|---|---|
33-i processen | Korveranta 450 | Finland | 450 kW PowerCont | - Delivery "keyturn" boiler in container - Container size 4,2*7,5*4,3 м - Fuel storage with spring system D 5.4 m - Fuel - wood chips, humidity 30-55% |
|
Objekt nr | Projekt | Land | Effekt/kW | Teknisk beskrivning |
---|---|---|---|---|
32-i processen | Vapo Lasipalatsi | Finland | 2000 | * Delivery "keyturn" boiler in container * Fuel Storage Build on place * Fuel - wood chips, humidity 30-55% |
![]() |
Kohteen nro | Nimitys | Maa | Tekninen kuvaus | Tekninen kuvaus |
---|---|---|---|---|
31 | HJO Bjornsson | Ruotsi | 999 Industrial | * Delivery "keyturn" boiler in container * Fuel Storage Build on place * Fuel - wood chips, humidity 30-55% * Mission - heating chicken farm |
|
Objekt nr | Projekt | Land | Effekt/kW | Teknisk beskrivning |
---|---|---|---|---|
30 | Martin –Sweden – 750 kW PowerCont | Sverige | 750 | * Boiler BMT Power 750 with moving grate * Module size 10m*4m*4m * Fuel storage capacity - 4*4 m, 67 m3 * Fuel - wood chips, humidity 30-55% * Cyclone flue gas cleaning up |
|